7EN52–0425-00

Replacing the battery

The following instructions for replacing the battery only apply to the socket meter, not the switchboard meter.
DANGER
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
  • Apply appropriate personal protective equipment (PPE) and follow safe electrical work practices. See NFPA 70E in the USA, CSA Z462 or applicable local standards.
  • Turn off all power supplying this device and the equipment in which it is installed before working on the device or equipment.
  • Always use a properly rated voltage sensing device to confirm that all power is off.
  • Ensure the meter has been unpowered for at least 15 minutes prior to starting work on the meter.
Failure to follow these instructions will result in death or serious injury.
  1. Remove the meter cover.
  2. Disconnect the battery wire harness connector from the meter.
      A Battery wire harness connector
      B Battery wire routing channel
      C Battery in battery slot
         
  3. Carefully pull out the battery wire from the routing channel.
  4. Remove the battery from its slot in the meter’s housing.
  5. Place the new battery in the battery slot in the meter’s plastic housing.
  6. Route the wire into the channel, then connect the wire harness connector.
  7. Replace the cover of the meter.
  8. Dispose of the old battery in accordance with local environmental regulations.
QR Code is a registered trademark of DENSO WAVE INCORPORATED in Japan and other countries.