Start a Battery Test
Prerequisites:
- 
                  The battery disconnect devices are closed. 
- 
                  No critical alarms present. 
- 
                  The bypass supply must be available. 
- 
                  Static bypass operation must be available. 
- 
                  The batteries must be more than 50% charged. 
- 
                  The runtime available must be more than 4 minutes. 
- 
                  The operation mode must be normal operation, eConversion, or ECO mode. 
- 
                  The system operation mode must be inverter, eConversion, or ECO mode. 
This feature performs a number of tests on the batteries, such as fuse-blown check and weak battery detection. The test will discharge the batteries and use about 10% of the total runtime capacity. Example: If you have 10 minutes of runtime, the test will run for 1 minute. The battery test can be scheduled to run automatically in different time intervals (from weekly and up to once a year).
- Select .
- Tap OK on the confirmation screen.