Start-up
![]() |
---|
HAZARD OF ELECTRIC SHOCK, EXPLOSION, or Arc Flash
Failure to follow these instructions will result in death or serious injury.
|
Training of personnel for final start-up can be provided. Contact your local Schneider Electric field sales representative for information.
Preliminary Start-Up Procedures
-
Turn off all main and control power supplying the equipment.
-
Vacuum every compartment. Remove all loose parts, tools, miscellaneous construction items, and litter.
-
Verify that all insulating boots are installed correctly and properly closed. Verify that primary cable connections are properly insulated.
-
Verify that any customer installed low voltage cables with ground shield maintain 6 inches distance from primary conductors.
-
Verify primary cable routing is properly installed as per instructions provided in previous sections.
-
Replace all of the main bus covers and any other barriers or covers that were removed during installation.
-
Install the cable compartment back covers.
-
Connect the battery charger and batteries (if used) to the switchgear control bus according to the order drawings.
-
Unblock all of the relays and set to the relay schedule. Using a relay tester, verify the settings and electrical operation of each relay.
-
Verify that any control power transformer used has the current limiting fuses in place. Pull the drawer out to the withdrawn position.
Installing and Testing Circuit Breakers in the TEST/DISCONNECT Position
Follow the steps for installing and testing the circuit breaker in the TEST/DISCONNECT position outlined in Circuit Breaker Operation.
Operation
Before energizing the equipment (If necessary, use an external control power source):
-
Rack one circuit breaker at a time following the steps outlined in Circuit Breaker Operation.
-
While in the Test/Disconnect position, electrically close and open the circuit breaker with the door-mounted circuit breaker control switch. Open the circuit breaker by temporarily closing the contacts of each protective relay. Reset the relay targets after each operation.
-
Electrically operate from remote control locations and check the remote indicating lights.
-
Operate all electrical interlocks, transfer schemes, lock-out relays, and other control functions to validate proper operation.
-
Remove the temporary source of low voltage power (if used) and make the permanent connection of low voltage power. Rack all circuit breakers to the Connected position.
-
If drawout fuses and drawout voltage transformers are included in the installation, rack them into the connected position by following the steps outlined in Voltage Transformer, Control Power Transformer, and Fuse Drawout Units.
-
Using a properly rated voltage sensing device, verify again that trip voltage is available at the circuit breaker control terminals in each compartment.
Energizing the Switchgear
To establish electrical service follow these steps:
-
Energize the incoming high voltage circuits.
-
Close the main circuit breakers.
-
Close the feeder circuit breakers.
-
Energize loads one at a time.
Removing Circuit Breakers
Follow the steps outlined in Circuit Breaker Operation.