Connect the Power Cables between the Easy UPS 3S Pro UPS and the Modular Battery Cabinet
- Remove the packaging bag without cutting it – save the packaging bag for later use.
- Remove the conduit box from the rear of the modular battery cabinet.
- Install the conduit box on the modular battery cabinet. Note that the conduit box is installed in the reverse position.
- Remove the top cover from the modular battery cabinet.
- Remove the installation kit from the top of the modular
battery cabinet. The installation kit contains DC cables, hardware,
and cable ties for interconnection between the modular battery cabinet
and the UPS.
- DC+ cable WH00141 (red)
- DC N cable WH00142 (blue)
- DC- cable WH00143 (white)
- PE cable WH00146 (yellow and green)
- Cut holes on the cable brush plate on the conduit box.
- Connect the supplied DC cables (DC+, DC-, DC N) to the
UPS.
- Connect the provided PE cable and the DC cables (DC+, DC-, DC N) in the modular battery cabinet.
- Route the PE cable and DC cables (DC+, DC-, DC N) out through the conduit box and into the UPS power cabling area.
- Follow the UPS installation manual to connect the PE
cable and DC cables (DC+, DC-, DC N) in the UPS. NOTE: The provided DC cables have an M6 connector on one end and an M8 connector on the other end. Select the appropriate connector size based on the UPS commercial reference. See DC Cable Connector Size Selection for details.
DC Cable Connector Size Selection
UPS commercial reference DC cable end connector size - in the UPS DC cable end connector size - in the modular battery cabinet E3SP10KH, E3SP15KH
E3SP20KH, E3SP30KH, E3SP40KH
E3SP15KHIN, E3SP20KHIN
E3SP30KHIN, E3SP40KHIN
E3SP10K3I, E3SP15K3I
E3SP20K3I, E3SP30K3I
E3SP15K3IIN, E3SP20K3IIN
E3SP30K3IIN
E3SP10KHB, E3SP15KHB
E3SP20KHB, E3SP30KHB
E3SP10K3IB, E3SP15K3IB
E3SP20K3IBM6 M8 E3SP40KHB
E3SP30K3IBM8 M6 - Fasten the power cables to the cable reliefs.