Unpack the System
| NOTE |
|---|
|
Parts delivered in separate packages
Be careful when unpacking the system that none of the
packages or bags with parts for installation are thrown away.
|
When any crate or frame have been removed continue to unpack the system by:
-
If applicable, remove the vacuum sealed aluminium foil or VCI plastic.
-
If applicable, remove any protective plastic, paper, felt and/or foam.
-
If applicable, remove any desiccant bags.
-
If applicable, remove any VCI-foam strips placed inside the system.
-
The system is delivered on a customized pallet.
-
Loose parts are delivered under the rain roof on top of the system and/or inside the cabinet.
-
The modules and any batteries will be delivered in a separate crate/pallet (typically either EUR-pallet or EUR-6-pallet).
-
Examine the inside of the system for any transportation damage. If any damage is found, immediately contact both the shipping agency and Gutor Service Center.
-
The system is now ready to be moved to the installation site. For more information see the Installation Manual.