Operation
![]() |
---|
HAZARD OF ELECTRIC SHOCK, EXPLOSION, or Arc Flash
Failure to follow these instructions will result in death or serious injury.
|
Training of personnel for final start-up can be provided. Contact your local Schneider Electric field sales representative for information.
Preliminary Start-Up Procedures
-
Turn off all main and control power supplying the equipment.
-
Vacuum every compartment. Remove all loose parts, tools, miscellaneous construction items, and litter.
-
Verify that all insulating boots are installed correctly and properly closed. Verify that primary cable connections are properly insulated.
-
Verify that any customer installed low voltage cables with ground shield maintain 6 inches distance from primary conductors.
-
Verify primary cable routing is properly installed as per instructions provided in previous sections.
-
Replace all of the main bus covers and any other barriers or covers that were removed during installation.
-
Install the cable compartment back covers.
-
Connect the battery charger and batteries (if used) to the switchgear control bus according to the order drawings.
-
Unblock all of the relays and set to the relay schedule. Using a relay tester, verify the settings and electrical operation of each relay.
-
Verify that any control power transformer used has the current limiting fuses in place. Pull the drawer out to the withdrawn position.
Installing and Testing Circuit Breakers in the TEST/DISCONNECT Position
Follow the steps for installing and testing the circuit breaker in the TEST/DISCONNECT position outlined in Schneider Electric Bulletin. 6055-41.
Circuit Breaker Preliminary Start-up Procedure
-
Electrically close and open the circuit breaker with the door-mounted circuit breaker control switch. OPEN (O) the circuit breaker by temporarily closing the contacts of each protective relay. Reset the relay targets after each operation.
-
Electrically operate from remote control locations and check the remote indicating lights.
-
Operate all electrical interlocks, transfer schemes, lock-out relays, and other control functions to validate proper operation.
-
Remove the temporary source of low voltage power (if used) and make the permanent connection of low voltage power.
-
Follow the steps outlined in “Racking the Circuit Breaker into the CONNECTED Position” in Schneider Electric Bulletin 6055-41.
-
Using the racking handle provided, rack the drawout fuses and drawout voltage transformers into the connected position.
-
Using a properly rated voltage sensing device, verify again that trip voltage is available at the circuit breaker terminals in each compartment.
Energizing the Switchgear
To establish electrical service follow these steps:
-
Energize the incoming high voltage circuits.
-
Close the main circuit breakers.
-
Close the feeder circuit breakers.
-
Energize loads one at a time.
Removing Circuit Breakers
Follow the directions outlined in “Racking the Circuit Breaker Out of the CONNECTED Position” in Schneider Electric Bulletin 6055-41.