Installation Procedure
- Lithium-ion battery cabinet(s): Prepare for Installation.
- UPS: Prepare for Installation.
- Only for UPS without preinstalled power modules: Install the Power Module(s).
- UPS: Install the Seismic Anchoring (Option).
- Lithium-ion battery cabinet(s): Install the Rear Seismic Anchoring.
- Lithium-ion battery cabinet(s): Position and Interconnect the Battery Cabinets.
- Lithium-ion battery cabinet(s): Install the Front Seismic Anchoring.
- Only for UPS for TN-C/480 V solid-grounded earthing system (no neutral connection): Prepare the UPS for TN-C/480 V Solid-Grounded System.
- UPS: Perform one of the following:
- UPS: Connect the Signal Cables.
- UPS: Connect the Signal Cables from Switchgear and Third-Party Auxiliary Products.
- UPS: Connect the External Communication Cables.
- UPS: Connect the Modbus Cables.
- UPS: Add Translated Safety Labels to Your Product.
- UPS: Final Installation.
- Lithium-ion battery cabinet(s): Install the Battery Modules in the Battery Cabinet.
- Lithium-ion battery cabinet(s): Connect the Power Cables.
- Lithium-ion battery cabinet(s): Route the Signal Cables to the Switchgear, Rack BMS, and System BMS Ports.
![]() |
---|
hAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
Startup must only be performed by Schneider Electric.
Failure to follow these instructions will result in death or serious injury.
|
For moving or decommissioning the UPS or the Lithium-ion battery cabinets after installation has been completed, see Decommission or Move the UPS to a New Location or Decommission or Move the Battery Cabinet to a New Location.