Specifications for Maintenance Bypass Cabinet with Input Transformer (GVSBPIT25, GVSBPIT50, GVSBPIT75)
UPS rating | 10 kW | 15 kW | 20 kW | 25 kW | 30 kW | 40 kW | 50 kW | 60 kW | 75 kW |
---|---|---|---|---|---|---|---|---|---|
Input voltage (V) | 480/600 | ||||||||
Input connections | 3-wire (L1, L2, L3, PE) | ||||||||
Nominal input current (A) | 13/10 | 19/15 | 26/20 | 32/26 | 38/31 | 51/41 | 64/51 | 82/67 | 100/81 |
Maximum input current (A) | 15/12 | 23/16 | 31/25 | 38/31 | 46/37 | 61/49 | 77/61 | 95/75 | 115/92 |
Output connections | 4-wire (L1, L2, L3, N, PE) | ||||||||
Output voltage (V) | 208 | ||||||||
Nominal output current (A) | 28 | 42 | 56 | 69 | 83 | 111 | 139 | 167 | 208 |
Frequency (Hz) | 60 | ||||||||
Circuit breaker interrupting ratings (kA) | 100 at 240 V (for UIB/MBB/UOB) | ||||||||
Continuous operation limited to maximum 110% load. |
Trip Settings for Maintenance Bypass Cabinet with Input Transformer
UPS rating | Breaker type | Ir setting | Tr at 6 Ir setting | Ir setting | Tr at 6 Ir setting | li (x In) setting |
---|---|---|---|---|---|---|
UIB/MBB/UOB | UIB | MBB/UOB | UIB/MBB/UOB | |||
10 kW | HJF36150CU31X | 50 | 0.5 | 50 | 0.5 | 1.5 |
15 kW | HJF36150CU31X | 60 | 0.5 | 50 | 4 | 1.5 |
20 kW | HJF36150CU31X | 80 | 0.5 | 70 | 4 | 1.5 |
25 kW | HJF36150CU31X | 100 | 0.5 | 80 | 4 | 1.5 |
30 kW | JJF36250CU31X | 110 | 4 | 100 | 4 | 1.5 |
40 kW | JJF36250CU31X | 150 | 4 | 150 | 4 | 1.5 |
50 kW | JJF36250CU31X | 200 | 0.5 | 175 | 2 | 1.5 |
60 kW | JJF36250CU31X | 250 | 4 | 225 | 1 | 2 |
75 kW | JJF36250CU31X | 250 | 4 | 250 | 2 | 2 |
Recommended Upstream Protection for Maintenance Bypass Cabinet with Input Transformer
For 480 V Input
UPS rating | Breaker type | Ir setting | Tr at 6 Ir setting | li (x In) setting |
---|---|---|---|---|
10 kW | HJL36060U31X | 15 | 4 | 6 |
15 kW | HJL36060U31X | 25 | 4 | 6 |
20 kW | HJL36060U31X | 30 | 4 | 6 |
25 kW | HJL36060U31X | 35 | 4 | 6 |
30 kW | HJL36060U31X | 45 | 4 | 12 |
40 kW | HJL36060U31X | 60 | 4 | 12 |
50 kW | HJL36100U31X | 70 | 4 | 8 |
60 kW | JJL36250CU31X | 100 | 0.5 | 2 |
75 kW | JJL36250CU31X | 100 | 0.5 | 2 |
For 600 V Input
UPS rating | Breaker type | Ir setting | Tr at 6 Ir setting | li (x In) setting |
---|---|---|---|---|
10 kW | HJL36060U31X | 15 | 1 | 6 |
15 kW | HJL36060U31X | 20 | 4 | 6 |
20 kW | HJL36060U31X | 25 | 4 | 6 |
25 kW | HJL36060U31X | 30 | 4 | 6 |
30 kW | HJL36060U31X | 35 | 8 | 12 |
40 kW | HJL36060U31X | 45 | 8 | 12 |
50 kW | HJL36060U31X | 60 | 4 | 12 |
60 kW | JJL36250CU31X | 100 | 0.5 | 2 |
75 kW | JJL36250CU31X | 100 | 0.5 | 2 |
Recommended Cable Sizes for Maintenance Bypass Cabinet with Input Transformer
![]() |
---|
hazard of electric shock, explosion, or arc flash
All wiring must comply with all applicable national and/or electrical codes. The maximum
allowable cable size is 4/0 AWG.
Failure to follow these instructions will result in death or serious injury.
|
Cable sizes in this manual are based on Table 310.15 (B)(16) of the National Electrical Code (NEC) with the following assertions:
-
90 °C (194 °F) conductors (75 °C (167 °F) termination)
-
An ambient temperature of 30 °C (86 °F)
-
Use of copper or aluminum conductors
If the ambient temperature is greater than 30 °C (86 °F), larger conductors are to be selected in accordance with the correction factors of the NEC.
Equipment grounding conductors/Protective Earth (PE in this manual) are sized in accordance with NEC Article 250.122 and Table 250.122.
Copper
UPS rating | 10 kW | 15 kW | 20 kW | 25 kW | 30 kW | 40 kW | 50 kW | 60 kW | 75 kW |
---|---|---|---|---|---|---|---|---|---|
Input phases (AWG/kcmil) | 8 | 8 | 8 | 8 | 4 | 4 | 4 | 3 | 1 |
Input PE (AWG/kcmil) | 10 | 10 | 10 | 10 | 10 | 8 | 8 | 6 | 6 |
Output phases (AWG/kcmil) | 8 | 8 | 4 | 4 | 3 | 1 | 2/0 | 3/0 | 4/0 |
Output PE (AWG/kcmil) | 10 | 10 | 8 | 8 | 8 | 6 | 6 | 4 | 4 |
Neutral (AWG/kcmil)* | 8 | 4 | 2 | 1 | 1/0 | 3/0 | 2 x 1 | 2 x 1/0 | 2 x 3/0 |
DC+/DC- (AWG/kcmil) | 10 | 6 | 4 | 4 | 2 | 1/0 | 1/0 | 4/0 | 2 x 1 |
DC PE (AWG/kcmil) | 10 | 10 | 8 | 8 | 6 | 6 | 6 | 4 | 4 |
Aluminum
UPS rating | 10 kW | 15 kW | 20 kW | 25 kW | 30 kW | 40 kW | 50 kW | 60 kW | 75 kW |
---|---|---|---|---|---|---|---|---|---|
Input phases (AWG/kcmil) | 6 | 6 | 6 | 6 | 2 | 2 | 2 | 1 | |
Input PE (AWG/kcmil) | 8 | 8 | 8 | 8 | 8 | 6 | 6 | 4 | |
Output phases (AWG/kcmil) | 6 | 6 | 3 | 2 | 1 | 3/0 | 4/0 | 2 x 1 | |
Output PE (AWG/kcmil) | 8 | 8 | 6 | 6 | 6 | 4 | 4 | 2 | |
Neutral (AWG/kcmil)* | 6 | 3 | 1 | 2/0 | 3/0 | 2 x 1 | 2 x 2/0 | 2 x 3/0 | |
DC+/DC- (AWG/kcmil) | 8 | 4 | 3 | 2 | 1/0 | 2/0 | 2/0 | ||
DC PE (AWG/kcmil) | 8 | 8 | 6 | 6 | 4 | 4 | 4 |