Recommended Upstream Protection and Cable Sizes – IEC
![]() |
---|
hazard of electric shock, explosion, or arc flash
An easily accessible breaker is required for upstream
protection. Maximum fault current disconnection time: 46 seconds at
200% input.
Failure to follow these instructions will result in death or serious injury.
|
Cable sizes in this manual are based on table B.52.12 and B.52.13 of IEC 60364-5-52 with the following assertions:
-
90 °C conductors
-
An ambient temperature of 30 °C
-
Use of copper or aluminum conductors
-
Installation method F4 for DC cables and installation method F5 for AC cables, corrected for single layer in perforated cable tray.
PE cables are sized in accordance with IEC 60364-5-54 table 54.2 Minimum cross-sectional area of protective conductors.
If the ambient temperature is greater than 30 °C, larger conductors are to be selected in accordance with the correction factors of the IEC.
NOTICE |
---|
Risk of equipment damage
To ensure correct load sharing in bypass operation in
a parallel system, the following recommendations apply:
Failure to follow these instructions can result in equipment damage.
|
NOTICE |
---|
Risk of unintentional device operation
If a residual current-operated protective device (RCD-B)
is used upstream as ground fault protection, then the RCD-B shall
be sized to not trip on the leakage current of this product, which
can be up to 200 mA.
Failure to follow these instructions can result in equipment damage.
|
Upstream Protection for IEC and Minimum Prospective Phase-To-Earth Short Circuit at the UPS Input/Bypass Terminals
![]() |
---|
Hazard of electric shock, explosion, or arc flash
The upstream overcurrent protective device (and its settings)
must be sized to ensure a disconnecting time within 0.2 seconds for
a minimum prospective phase-to-earth short circuit current calculated
or measured at the input/bypass terminals of the UPS.
Failure to follow these instructions will result in death or serious injury.
|
Recommended Upstream Protection and Cable Sizes for 500 kW UPS
Maximum OCPD (A) | Cable size per phase (mm2) Copper / Aluminum |
PE cable
size (mm2) Copper / Aluminum |
||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Voltage (V) | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 |
Input | 1000 Ir=0.90 |
1000 Ir=0.90 |
1000 Ir=0.90 |
1000 Ir=0.90 |
2x240/ 3x185 |
2x240/ 3x185 |
2x240/ 3x185 |
2x240/ 3x185 |
1x240/ 2x150 |
1x240/ 2x150 |
1x240/ 2x150 |
1x240/ 2x150 |
Bypass | 800 Ir=0.98 |
800 Ir=0.95 |
800 Ir=0.9 |
800 Ir=0.9 |
2x185/ 2x240 |
2x150/ 2x240 |
2x150/ 2x240 |
2x150/ 2x240 |
1x185/ 1x240 |
1x150/ 1x240 |
1x150/ 1x240 |
1x150/ 1x240 |
Output | 800 Ir=0.98 |
800 Ir=0.95 |
800 Ir=0.9 |
800 Ir=0.9 |
2x185/ 2x240 |
2x150/ 2x240 |
2x150/ 2x240 |
2x150/ 2x240 |
1x185/ 1x240 |
1x150/ 1x240 |
1x150/ 1x240 |
1x150/ 1x240 |
Battery | 1500 | 1500 | 1500 | 1500 | 3x185/ 3x240 |
3x185/ 3x240 |
3x185/ 3x240 |
3x185/ 3x240 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
Recommended Upstream Protection and Cable Sizes for 625 kW UPS
Maximum OCPD (A) | Cable size per phase (mm2) Copper / Aluminum |
PE cable
size (mm2) Copper / Aluminum |
||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Voltage (V) | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 |
Input |
1250 |
1250 |
1250 |
1250 Ir=0.9 |
3x185/ 3x240 |
3x185/ 3x240 |
3x185/ 3x240 |
3x185/ 3x240 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
Bypass | 1000 Ir=0.98 |
1000 Ir=0.95 |
1000 Ir=0.9 |
1000 Ir=0.9 |
2x240/ 3x240 |
2x240/ 3x185 |
2x240/ 3x185 |
2x240/ 3x185 |
1x240/ 2x185 |
1x240/ 2x150 |
1x240/ 2x150 |
1x240/ 2x150 |
Output | 1000 Ir=0.98 |
1000 Ir=0.95 |
1000 Ir=0.9 |
1000 Ir=0.9 |
2x240/ 3x240 |
2x240/ 3x185 |
2x240/ 3x185 |
2x240/ 3x185 |
1x240/ 2x185 |
1x240/ 2x150 |
1x240/ 2x150 |
1x240/ 2x150 |
Battery | 2000 | 2000 | 2000 | 2000 | 3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 4x240 |
2x185/ 2x240 |
2x185/ 2x240 |
2x185/ 2x240 |
2x185/ 2x240 |
Recommended Upstream Protection and Cable Sizes for 750 kW UPS
Maximum OCPD (A) | Cable size per phase (mm2) Copper / Aluminum |
PE cable
size (mm2) Copper / Aluminum |
||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Voltage (V) | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 |
Input | 1600 Ir=0.9 |
1600 Ir=0.9 |
1600 Ir=0.9 |
1250 Ir=1.0 |
3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 4x240 |
3x185 4x240 |
2x185/ 2x240 |
2x185/ 2x240 |
2x185/ 2x240 |
2x150/ 2x240 |
Bypass | 1250 Ir=0.95 |
1250 Ir=0.9 |
1250 Ir=0.9 |
1000 Ir= 1.0 |
3x185/ 4x185 |
3x185/ 3x240 |
3x185/ 3x240 |
2x240/ 3x240 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
1x240/ 2x185 |
Output | 1250 Ir=0.95 |
1250 Ir=0.9 |
1250 Ir=0.9 |
1000 Ir=1.0 |
3x185/ 4x185 |
3x185/ 3x240 |
3x185/ 3x240 |
2x240/ 3x240 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
1x240/ 2x185 |
Battery | 2500 | 2500 | 2500 | 2500 | 4x240/ 5x240 |
4x240/ 5x240 |
4x240/ 5x240 |
4x240/ 5x240 |
2x240/ 3x240 |
2x240/ 3x240 |
2x240/ 3x240 |
2x240/ 3x240 |
Recommended Upstream Protection and Cable Sizes for 800 kW UPS
Maximum OCPD (A) | Cable size per phase (mm2) Copper / Aluminum |
PE cable
size (mm2) Copper / Aluminum |
||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Voltage (V) | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 |
Input | 1600 Ir=0.9 |
1600 Ir=0.9 |
1600 Ir=0.9 |
1600 Ir=0.9 |
3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 4x240 |
2x185/ 2x240 |
2x185/ 2x240 |
2x185/ 2x240 |
2x185/ 2x240 |
Bypass | 1250 Ir=1.0 |
1250 Ir=0.95 |
1250 Ir=0.9 |
1250 Ir=0.9 |
3x185/ 4x240 |
3x185/ 4x185 |
3x185/ 3x240 |
3x185/ 3x240 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
Output | 1250 Ir=1.0 |
1250 Ir=0.95 |
1250 Ir=0.9 |
1250 Ir=0.9 |
3x185/ 4x240 |
3x185/ 4x185 |
3x185/ 3x240 |
3x185/ 3x240 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
2x150/ 2x185 |
Battery | 2500 | 2500 | 2500 | 2500 | 4x240/ 5x240 |
4x240/ 5x240 |
4x240/ 5x240 |
4x240/ 5x240 |
2x240/ 3x240 |
2x240/ 3x240 |
2x240/ 3x240 |
2x240/ 3x240 |
Recommended Upstream Protection and Cable Sizes for 1000 kW UPS
Maximum OCPD (A) | Cable size per phase (mm2) Copper / Aluminum |
PE cable
size (mm2) Copper / Aluminum |
||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Voltage (V) | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 |
Input | 2000 Ir=0.9 |
2000 Ir=0.9 |
2000 Ir=0.9 |
2000 Ir=0.9 |
4x240/6x240 | 4x240/6x240 | 4x240/6x240 | 4x240/6x240 | 2x240/3x240 | 2x240/3x240 | 2x240/3x240 | 2x240/3x240 |
Bypass | 1600 Ir=0.98 |
1600 Ir=0.95 |
1600 Ir=0.9 |
1600 Ir=0.9 |
4x185/5x240 | 4x185/5x240 | 3x240/4x240 | 3x240/4x240 | 2x185/3x240 | 2x185/3x240 | 2x185/2x240 | 2x185/2x240 |
Output | 1600 Ir=0.98 |
1600 Ir=0.98 |
1600 Ir=0.9 |
1600 Ir=0.9 |
4x240/6x240 | 4x240/6x240 | 3x240/6x240 | 3x240/6x240 | 2x240/3x240 | 2x240/3x240 | 2x240/3x240 | 2x240/3x240 |
Battery | 3300 | 3300 | 3300 | 3300 | 5x240/7x240 | 5x240/7x240 | 5x240/7x240 | 5x240/7x240 | 3x240/4x240 | 3x240/4x240 | 3x240/4x240 | 3x240/4x240 |
Recommended Upstream Protection and Cable Sizes for 1100 kW UPS
Maximum OCPD (A) | Cable size per phase (mm2) Copper / Aluminum |
PE cable
size (mm2) Copper / Aluminum |
||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Voltage (V) | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 |
Input | 2000 Ir=0.98 |
2000 Ir=0.98 |
2000 Ir=0.98 |
2000 Ir=0.95 |
4x300/ 5x300 |
4x300/ 5x300 |
4x300/ 5x300 |
4x300/ 5x300 |
2x300/ 3x300 |
2x300/ 3x300 |
2x300/ 3x300 |
2x300/ 3x300 |
Bypass | 2000 Ir=0.9 |
2000 Ir=0.9 |
1600 Ir=0.98 |
1600 Ir=0.95 |
4x240/ 5x300 |
4x240/ 5x300 |
3x300/ 4x300 |
3x300/ 4x300 |
2x240/ 3x300 |
2x240/ 3x300 |
2x240 2x300 |
2x240/ 2x300 |
Output | 2000 Ir=0.9 |
2000 Ir=0.9 |
1600 Ir=0.98 |
1600 Ir=0.95 |
4x240/ 5x300 |
4x240/ 5x300 |
3x300/ 4x300 |
3x300/ 4x300 |
2x240/ 3x300 |
2x240/ 3x300 |
2x240 2x300 |
2x240/ 2x300 |
Battery | 3300 | 3300 | 3300 | 3300 | 5x300/ 7x300 |
5x300/ 7x300 |
5x300/ 7x300 |
5x300/ 7x300 |
3x300/ 4x300 |
3x300/ 4x300 |
3x300/ 4x300 |
3x300/ 4x300 |
Recommended Upstream Protection and Cable Sizes for 1250 kW UPS
Maximum OCPD (A) | Cable size per phase (mm2) Copper / Aluminum |
PE cable
size (mm2) Copper / Aluminum |
||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Voltage (V) | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 |
Input | 2500 Ir=0.9 |
2500 Ir=0.9 |
2500 Ir=0.9 |
2500 Ir=0.9 |
5x240/ 6x300 |
5x240/ 6x300 |
5x240/ 6x300 |
5x240/ 6x300 |
3x240/ 3x300 |
3x240/ 3x300 |
3x240/ 3x300 |
3x240/ 3x300 |
Bypass | 2000 Ir=0.98 |
2000 Ir=0.95 |
2000 Ir=0.9 |
2000 Ir=0.9 |
4x300/ 5x300 |
4x300/ 5x300 |
4x240/ 5x300 |
4x240/ 5x300 |
2x300/ 3x300 |
2x300/ 3x300 |
2x240/ 3x300 |
2x240/ 3x300 |
Output | 2000 Ir=0.98 |
2000 Ir=0.95 |
2000 Ir=0.9 |
2000 Ir=0.9 |
4x300/ 5x300 |
4x300/ 5x300 |
4x240/ 5x300 |
4x240/ 5x300 |
2x300/ 3x300 |
2x300/ 3x300 |
2x240/ 3x300 |
2x240/ 3x300 |
Battery | 4000 | 4000 | 4000 | 4000 | 6x300/ 7x300 |
6x300/ 7x300 |
6x300/ 7x300 |
6x300/ 7x300 |
3x300/ 4x300 |
3x300/ 4x300 |
3x300/ 4x300 |
3x300/ 4x300 |
Recommended Upstream Protection and Cable Sizes for 1500 kW UPS
Maximum OCPD (A) | Cable size per phase (mm2) Copper / Aluminum |
PE cable
size (mm2) Copper / Aluminum |
||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Voltage (V) | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 | 380 | 400 | 415 | 440 |
Input | 3200* | 3200* | 3200* | 2500* | 7x240/ 9x240 |
7x240/ 9x240 |
7x240/ 9x240 |
6x240/ 8x240 |
4x240/ 5x240 |
4x240/ 5x240 |
4x240/ 5x240 |
3x240/ 4x240 |
Bypass | 2500* | 2500* | 2500* | 2000* | 6x240/ 7x240 |
5x240/ 7x240 |
5x240/ 7x240 |
5x240/ 6x240 |
3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 3x240 |
Output | 2500* | 2500* | 2500* | 2000* | 6x240/ 7x240 |
5x240/ 7x240 |
5x240/ 7x240 |
5x240/ 6x240 |
3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 4x240 |
3x240/ 3x240 |
Battery | 4000 | 4000 | 4000 | 4000 | 8x240/ 10x240 |
8x240/ 10x240 |
8x240/ 10x240 |
8x240/ 10x240 |
4x240/ 5x240 |
4x240/ 5x240 |
4x240/ 5x240 |
4x240/ 5x240 |