Start a Battery Test
Prerequisites:
-
The battery disconnect devices are closed.
-
No critical alarms present.
-
The bypass supply must be available.
-
Static bypass operation must be available.
-
The batteries must be more than 50% charged.
-
The runtime available must be more than 4 minutes.
-
The operation mode must be normal operation, eConversion, or ECO mode.
-
The system operation mode must be inverter, eConversion, or ECO mode.
This feature performs a number of tests on the batteries, such as fuse-blown check and weak battery detection. There are two types of battery tests (by capacity or by voltage/time) which are set up during battery configuration. See Configure the Battery Solution for details. The battery test by capacity can be scheduled to run automatically in different time intervals (from weekly and up to once a year).
- Select .
- Tap OK on the confirmation screen.