Installation Procedure
![]() |
---|
Hazard of electric shock, explosion, or arc flash
The UPS must be secured against movement. Perform one
of the following actions/procedures once the UPS is in its final position:
Failure to follow these instructions will result in death or serious injury.
|
![]() |
---|
TILTING HAZARD
The cabinet is top heavy - move with care and use ramps
over uneven floors.
Failure to follow these instructions can result in death, serious injury, or equipment
damage.
|
- Perform one of the following procedures:
- Without seismic anchoring: Position the UPS, or
- With seismic anchoring: Install the Seismic Anchoring (Option).
- Perform one of the following procedures:
- Top cable entry: Prepare the UPS for Top Cable Entry, or
- Bottom cable entry: Follow the installation manual provided with the bottom entry cabinet.
- Only for TN-C earthing system: Prepare for TN-C Earthing System.
- Only for UPS with one internal switch: Install the Neutral Disconnection Kit (Option).
- Perform one of the following procedures:
- Connect the Signal Cables.
- Connect the Signal Cables from Switchgear and Third-Party Auxiliary Products.
- Connect the Modbus Cables.
- Only for parallel system: Connect the PBUS Cables.
- Install the Power Module(s).
- Install the Redundant Intelligence Module Kit (Option).
- Final Installation.