Start Up the RPP
Follow these steps for first start-up and any time that the system is restarted after having been shut completely down with no power applied to the system.
- Verify the following before starting the RPP:
- The upstream input breaker is in the open (OFF) position.
- The input power cables have been correctly connected to the main input breaker(s) in the RPP. See Connect the Input Cables for details.
- Phase sequence on input is correct.
- The load power cables have been connected correctly to the branch breakers. See Connect the Load to the Branch Breakers for details.
- Correct torque has been applied to all power connections. See Torque Specifications for details.
- Voltage connected to the RPP matches the RPP nameplate and model number.
- All equipment has been properly grounded.
- All signal cables are installed correctly.
- All ventilation areas are free for obstructions that might impair proper airflow.
- Close the upstream input breaker.
- Close the main input breaker(s) in the RPP.
- Verify the function of the installed power meters in the RPP.
- Close the individual branch breakers in the RPP as required.
Verify normal operation of the RPP immediately after the start-up has been performed.
Use the display to verify proper readings from all circuits.
- For the first start-up of the RPP, perform the following
steps to enable configuration via the display:
- Access the web interface for the network management, see Access a Configured Network Management Interface.
- At first user login, the user name and password are apc – you will be prompted to change the password at first login.
- Create new users and configure user permissions.
- Enable/disable communication protocols as needed.
- Configuration via the display is now enabled.