DOCA0343EN-02

Assembling the Flex-Server

Refer to the below table for physical description and dimensions:

Description

Image

Mounting bracket for Flex-Server

Mounting bracket for LoRa and RS485

Flex-Server dimensions

Flex-Server

Wi-Fi antenna

4G antenna

Power supply

LoRa Connector

RS485 Converter

Perform the following steps to install the Flex-Server on mounting bracket with power supply:

NOTE: The Flex-Server must be installed ≥ 2.1 m (6.889 ft) above the ground level:

  1. Mark the positions of two drilling holes on the surface to install the mounting bracket.

  2. Drill two holes using a drill bit of 6 mm diameter.

  3. Install the mounting bracket on the surface with two M4 x 25 mm self-tapping screws.

  4. Tighten the screws using PH1 screwdriver.

  5. Slide the Flex-Server on the mounting bracket.

    DANGER
    HAZARD OF ELECTRIC SHOCK, EXPLOSION OR ARC FLASH
    • Turn off all power supplying this equipment before working on or inside equipment.
    Failure to follow these instructions will result in death or serious injury.
  6. Do the necessary wiring. Refer to the EcoStruxure Flex-Server Installation Sheet - ZEN0000102.

    NOTE: Use 0.2 A fuse with appropriate line to main voltage between AC power supply and mains.

Perform the following steps to install the LoRa connector and RS485I on mounting bracket:

  1. Mark the positions of two drilling holes on the surface to install the mounting bracket.

  2. Drill two holes using a drill bit of 6 mm diameter.

  3. Install the mounting bracket on the surface with two M4 x 25 mm self-tapping screws.

  4. Tighten the screws using PH1 screwdriver.

  5. Install two M3 x 6 mm flat head screws on the dedicated screw slot present on mounting bracket.

  6. Hang the RS485 converter on the two M3 x 6 mm flat head screws installed on the mounting bracket.

  7. Install the LoRa connector on the mounting bracket with two M4 x 25 mm self tapping screws.

  8. Tighten the screws using PH1 screwdriver.

Cellular Configuration:

NOTICE
REDUCED DEVICE PERFORMANCE
  • This device is for indoor use only and is not suitable for wet locations.
  • Do not install the device close to an exterior window.
  • When replacing a device, install the new device in the same position and direction as the replaced device.
Failure to follow these instructions can result in equipment damage.
  1. In case of a cellular configuration, open the four screws on the sides of the Flex-Server and carefully open the box, without removing the antenna cables. Insert a micro-SIM card and close the Flex-Server.

  2. Attach the Wi-Fi antenna to the Wi-Fi antenna connector on Flex-Server.

  3. Attach the 4G antenna to the 4G antenna connector on Flex-Server.

  4. Slide the Flex-Server on the mounting bracket.

  5. The new power supply has + and -ve to be connected to the Flex-Server’s +ve and -ve.

  6. Connect the Modbus or the BACnet to the RS485 port on the Flex-Server.

  7. Connect Modbus or the BACnet to the RS485 converter using the manual provided with the RS485 converter.

  8. Connect the LoRa module using the USB cable provided in the box.

  9. Connect the RS485 converter with the USB cable provided in the box.

  10. Plug the Power Supply Adaptor.

  11. Switch on the AC mains power supply.

QR Code is a registered trademark of DENSO WAVE INCORPORATED in Japan and other countries.

Was this helpful?