Pre-requisites
Once the equipment is received, installed, and connected in its operating location, the following points must be performed before operating the PowerLogic™ DVR system:
-
Check the input and output connections:
-
The wire must be adequate.
-
The terminals must be fitted correctly.
-
Check the tightening torque corresponding to the screws used in each case.
-
Check that the input and output phase sequences are correct.
-
-
Make sure that the power connected to the equipment does not exceed the nominal value.
-
Verify the fuses F1, F2, F3, F4, F5, and F6 of each PowerLogic™ DVR unit are in good condition and fitted correctly.
-
Check that the internal switch I1 of the PowerLogic™ unit is in DISABLE START position.
-
Check that all loads are OFF.
-
Check the installation and wiring connections to make sure that there are no short circuits or uninsulated parts.