Transport of the Cubicle with Crane
![]() |
---|
hazard of equipment damage
Failure to follow these instructions can result in injury or equipment damage.
|
Follow the below steps to transport the cubicles using crane:
-
Attach four crane ropes/chains (observe minimum carrying capacity and length). Lift the cubicle carefully.
NOTE:-
Lifting cables must be secured firmly before lifting. Good practices of the lifting must be followed.
-
-
Release the screw-fastenings between the lateral fixing brackets (1) on the pallet (2) and the cubicle.
-
Place the cubicle carefully on the floor at the intended site of installation.
Figure 11
Switchgear Cubicle Transport with
Crane
1 |
Fixing brackets |
4 |
Plane washer M10 |
2 |
Pallet |
5 |
Allen screw M10 x 35 |
3 |
Lifting brackets |