BQT6904400-01

Transport of the VCB

Follow the below steps to lift and deposit the VCB.

  1. Install the lifting hooks on the side plates of the VCB as shown below.


    Figure 12
    Install the Lifting Hooks


  2. When handling, guide the VCB roughly in horizontal position by the front cover as shown below.


    Figure 13
    Guide the VCB