Configuring basic setup parameters
- Double-click on Basic Setup to open the dialog showing the list of parameters.
- Select a parameter and click Edit to open its specific setup dialog.Parameter Options Description System Type 1Ph 2Wire L-N - Number of CTs- 
                                                (1) One CT on I1 
 
- 
                                                
- 
                                          Number of VTs - 
                                                (0) Direct Connect 
 
- 
                                                
 Step 1: Select this when the meter is wired to measure a single-phase 2 wire line-to-neutral power system, and then click Next. Step 2: Choose the Number of CTs and Number of VTs from the Set System Options, and then click Finish. 1Ph 2Wire L-L - Number of CTs- 
                                                (1) One CT on I1 
 
- 
                                                
- 
                                          Number of VTs - 
                                                (0) Direct Connect 
 
- 
                                                
 Step 1: Select this when the meter is wired to measure a single-phase 2 wire line-to-line power system, and then click Next. Step 2: Choose the Number of CTs and Number of VTs from the Set System Options, and then click Finish. 1Ph 3Wire L-L with N - Number of CTs- 
                                                (2) Two CTs on I1 I2 
 
- 
                                                
- 
                                          Number of VTs - 
                                                (0) Direct Connect 
 
- 
                                                
 Step 1: Select this when the meter is wired to measure a single-phase 3 wire line-to-line with grounded neutral power system, and then click Next. Step 2: Choose the Number of CTs and Number of VTs from the Set System Options, and then click Finish. 3Ph 3Wire Ungrounded Delta - Number of CTs- 
                                                (1) One CT on I1 
- 
                                                (2) Two CTs on I1 I3 
- 
                                                (3) Three CTs 
 
- 
                                                
- 
                                          Number of VTs - 
                                                (2) Two VTs on V1 V3 
- 
                                                (0) Direct Connect 
 
- 
                                                
 Step 1: Select this when the meter is wired to measure a 3 phase 3 wire ungrounded delta power system, and then click Next. Step 2: Choose the Number of CTs and Number of VTs from the Set System Options, and then click Finish. 3Ph 4Wire Grounded Wye (Default) - Number of CTs- 
                                                (1) One CT on I1 
- 
                                                (2) Two CTs on I1 I3 
- 
                                                (3) Three CTs 
 
- 
                                                
- 
                                          Number of VTs - 
                                                (3) Three VTs 
- 
                                                (0) Direct Connect 
 
- 
                                                
 Step 1: Select this when the meter is wired to measure a 3 phase 4 wire grounded Wye power system, and then click Next. Step 2: Choose the Number of CTs and Number of VTs from the Set System Options, and then click Finish. 1PH4W Multi L with N - Number of CTs- 
                                                (2) Two CTs on I1 I2 
- 
                                                (3) Three CTs 
 
- 
                                                
- 
                                          Number of VTs - 
                                                (0) Direct Connect 
 
- 
                                                
 Step 1: Select this when the meter is wired to measure multiple loads on a single-phase line-to-neutral power system, and then click Next. Step 2: Choose the Number of CTs and Number of VTs from the Set System Options, and then click Finish. CT Primary 1 to 32767 (Default: 100)Enter the size of the CT primary, in Amps. CT Secondary 1 Amp 5 Amp (Default: 1000 mV)Select the size of the CT secondary, in millivolts. VT Primary 1 to 1000000 (Default: 100)Enter the size of the VT primary, in Volts. VT Secondary - 100 Volts
- 110 Volts
- 115 Volts
- 120 Volts
 Select the size of the VT secondary, in Volts. Nominal Frequency - 50 Hz
- 60 Hz
 Select the frequency of the electrical power system, in Hertz. 
- Number of CTs
- Click OK, and then click Send to save your changes to the meter.NOTE: When changes are not saved to the meter, the status bar on the bottom left screen shows Download Incomplete.