Perform a Primary Injection Test
Description
DANGER |
|---|
|
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
Perform a primary injection test to check that the MicroLogic Active control unit is able to provide standard protection functions.
Failure to follow these instructions will result in death or serious injury.
|
A primary injection test is mandatory to check that trip system connections have been correctly made and that the MicroLogic Active control unit is able to provide standard protection functions, for example tripping the circuit breaker in case of an electrical network incident. The test is performed by injecting a controlled current from an external power source, into the primary circuit of the circuit breaker.
Preparing the Primary Injection Test
A wiring diagram of the primary injection test kit for MasterPacT MTZ1 and MasterPacT MTZ2 circuit breakers is illustrated below.
Use 2.5 mm2 cables between R1 and CTR1.
|
B1 |
MCB circuit breaker 10 A |
|
T1 |
Transformer 250 VA |
|
B2 |
MCB circuit breaker 16 A |
|
CTR1 |
Control relay |
|
P.B. |
Pushbutton |
|
R1 |
Resistance 300 W - 2.2 Ohms |
|
J1 |
Jaws for connection to the upstream and equivalent downstream of one pole |
Bill of Materials
Schneider Electric recommends the following components for the primary injection test kit for MasterPacT MTZ1 and MasterPacT MTZ2 circuit breakers.
|
Schematic reference |
Item |
Supplier |
Reference |
Quantity |
|---|---|---|---|---|
|
B1 |
Circuit breaker DT40 – 10 A + Vigi 30 mA |
Schneider Electric |
A9D55610 |
1 |
|
T1 |
Transformer 250VA 220 Vac – 24 Vac |
BLOCK |
FST 250/24 |
1 |
|
B2 |
Circuit breaker DT40 – 16 A + Vigi 30 mA |
Schneider Electric |
A9N21025+ A9N21454 |
1 |
|
CTR1 |
Auxiliary Zelio relay |
Schneider Electric |
RSB2A080B7 |
1 |
|
P.B |
Pushbutton with normally open contact |
Schneider Electric |
XB4BL41 |
1 |
|
R1 |
Resistor 2.2 ohms – 300 W |
WIDAP |
160169 |
1 |
|
Conrad |
1525215 |
1 |
||
|
J1 |
Jaws |
GRELUMA |
ZL373LUM |
2 |
|
– |
Terminal block for multimeter connection |
Schneider Electric |
47075 |
2 |
Performing the Primary Injection Test
|
Step |
Action |
|---|---|
|
1 |
Disconnect the circuit breaker from the switchboard network before starting. |
|
2 |
Charge the mechanism by pulling the spring charging handle down seven times. |
|
3 |
Close the circuit breaker by pressing the closing pushbutton on the front of the circuit breaker. |
|
4 |
Connect the primary circuit of the circuit breaker to the kit using the jaws (J1), as shown in the wiring diagram above.
Connect the external power source to the upstream and downstream of one pole. |
|
5 |
|
|
6 |
Press the pushbutton to inject current into the circuit breaker. |
|
7 |
Wait until the voltage reading is greater than 1 Vdc. |
|
8 |
The test passes if the measured voltage is greater than 1 Vdc. |
DANGER