Verifying the System Wiring
After all required and optional parameters have been configured and you have tested the functionality of the power devices, check the system wiring, which can include:
- 
               
               
Power wiring (see the table below)
 - 
               
               
Bus coupler connections (see the table below)
 - 
               
               
I/O wiring
 - 
               
               
SIL* interface module wiring
 - 
               
               
Voltage interface module wiring
 
Perform the steps in the following table to verify the power wiring.
Verify the Power Wiring
| 
                        
                         Step  | 
                     
                     
                        
                         Action  | 
                     ||
|---|---|---|---|
| 
                        
                         1  | 
                     
                     
                        
                         Visually confirm that the actual power wiring matches the intended power wiring, as described in the power wiring diagram.  | 
                     ||
| 
                        
                         2  | 
                     
                     
                        
                         Look for any detected trips or notifications in the OMT or DTM.  | 
                     ||
Verify the Bus Coupler Connections
| 
                        
                         Step  | 
                     
                     
                        
                         Action  | 
                     ||
|---|---|---|---|
| 
                        
                         1  | 
                     
                     
                        
                         Verify that the Fieldbus connections are in place.  | 
                     ||
| 
                        
                         2  | 
                     
                     
                        
                         Verify that the 24 V control power connection is securely in place.  | 
                     ||
| 
                        
                         3  | 
                     
                     
                        
                         Verify that the flat cables from the bus coupler to all modules are securely in place  | 
                     ||