Installation of the Changeover Connection Kits
This section describes the installation procedure of changeover connection kits on the power terminals of the contactors.
-
Place the coupling bar beside the downstream power terminals of the contactors.
-
Place the bars to connect the line on the downstream power terminals of one of the contactors.
-
Insert the screws and washers through the coupling bar and power terminals.
-
Tighten the screws at the right torque.
Contactor |
Tool |
Torque |
Screws |
---|---|---|---|
LC1G205-245C |
Allen key |
18 ± 1.8 N•m |
M8 |
LC1G300-475C |
Inner hexagon |
35 ± 3.5 N•m |
M10 |
LC1G620C |
Inner hexagon |
58 ± 5.8 N•m |
M12 |