General Principle to Commission an EcoStruxure Panel Server
Overview
The commissioning of an EcoStruxure Panel Server can be performed using one of the following tools:
-
EcoStruxure Power Commission (EPC) software (recommended). See EcoStruxure Power Commission Online Help.
Use the software for a system-focused, global approach to configure the EcoStruxure Panel Server and all the devices in the switchboard. In addition, the software advanced features allow you to:
-
prepare a project off-line.
-
save a project (system configuration).
-
create a new project from an existing one.
-
generate a report with data collected during configuration testing and to retrieve the settings updated through the EcoStruxure Panel Server webpages.
-
to export a project to a supervision software(for example, EcoStruxure Power Monitoring Expert).
-
-
EcoStruxure Panel Server webpages.
Use the webpages for a device-focused approach to modify some settings in the EcoStruxure Panel Server.
During commissioning the EcoStruxure Panel Server, update the firmware of the EcoStruxure Panel Server.
Pre-requisites to Commissioning
To commission the EcoStruxure Panel Server, connect it to Ethernet (see Connection to a PC).