iMCC Communications
NOTICE |
---|
LOSS OF COMMUNICATIONS
Failure to follow these instructions can result in equipment damage.
|
Before energizing the equipment, check the items below to verify that the iMCC networking and cabling are set up and connected properly.
-
Cabling Connections
-
Verify that the network length without a repeater is less than 1500 feet (457 m).
-
Verify that the MCC cables are connected between shipping splits. See Cables Between Shipping Splits for instructions.
-
Verify that each device tap cable is properly connected to the main trunk line.
-
Verify that all network connections are secure.
-
Verify that terminating resistors are installed as required per network protocol.
Communications Setup
-
Verify that all devices have been assigned correct addresses; see Device Addressing for specific addressing parameters.